City of Santa Monica Soft-Story Retrofit Services
Milestones
Building Type
- Soft Story – >2 stories & <16 units
- Soft Story – 16+ units
- Soft Story – 2 stories, 7–15 units
- Soft Story – 2 stories, <7 units
- Soft Story – 2 stories, <7 units (2nd batch)
Evaluation Due
- Sept 2021
- Oct 2021
- Nov 2021
- May 2022
- July 2022
Plans Due
- Sept 2022
- Oct 2022
- Nov 2022
- May 2023
- July 2023
Retrofit Complete
- Sept 2025
- Oct 2025
- Nov 2025
- May 2026
- July 2026
Professional Engineering, Screening Reports, Retrofit Plans & Permit Support
Santa Monica adopted its Seismic Retrofit Ordinance in 2017 to reduce the risk of structural failures during earthquakes. More than 2,000 commercial and multi-family residential buildings were identified as potentially vulnerable and required to comply with retrofit regulations.
If your property appears on the City’s soft-story list, completing the required evaluation and retrofit (if applicable) is mandatory. Below is a clear breakdown of the Santa Monica process, compliance deadlines, and how Socal Structural can assist.
Who Must Comply?
- Wood-framed
- Two or more storiesv
- Built before January 1, 1978
- Ground-floor parking / garages / open fronts
- One or more soft, weak, or open-front wall lines
Single-family residences are not included. Some detached accessory units may qualify for exemption review.
Is Your Building On the List?
Santa Monica provides two tools for property owners to confirm whether their building has been identified as potentially vulnerable:
- Searchable map
- Open Data list (downloadable)
Inclusion on the City’s list does not automatically mean your building is unsafe, only that it falls within a building category subject to evaluation under the ordinance.
A California-licensed structural or civil engineer (or a registered architect) must complete a full structural evaluation of the building to determine whether it meets minimum earthquake performance standards.
The completed evaluation must be submitted to the City’s Building & Safety Division (Email: seismic@santamonica.gov)
Outcomes:
- If the building meets minimum seismic performance → it may be exempted from retrofit requirements.
- If the building does not meet minimum standards → retrofit is required and the project proceeds to plan review.
- Only properly licensed contractors may pull the permit.
- Work must begin within six months of permit issuance to avoid expiration.
- Inspections will be performed periodically during construction.
A final inspection from a City Building Inspector is required.
Once approved, the Inspector will issue a Final sign-off on the permit, this is the City’s official verification that the building is fully compliant.
This is the final step for closing out your seismic retrofit obligation
How Socal Can Help?
- Structural evaluation by licensed engineers
- Preparation of retrofit plans and calculations
- Tenant-occupied Means & Methods Plans
- Electronic plan review submittals
- Construction support and inspection coordination
- End-to-end project management until Final sign-off
Frequently Asked Questions
How do I know if my building is included?
Does being listed mean my building is hazardous?
Who can perform the Structural Evaluation?
- California Licensed Structural Engineer
- California Licensed Civil Engineer
- Registered Architect