What do I need to do?
Screening Report
- Due one year from your Notice to Comply date. A licensed engineer evaluates your building and determines whether it's exempt (no retrofit required) or requires a retrofit.
Retrofit Plans
- Due two years from notice. If a retrofit is required, a complete engineered plan set has to be submitted to the City.
Permit and Start Construction
- Due three to four years from notice. Once the City approves the plans, a contractor pulls the permit and construction must begin within one year.
Complete Construction
- Due five years from notice. The City performs a final inspection and closes the permit with "Final" status.
Full Engineering Support, Start to Finish
Culver City now requires soft-story buildings to comply with Ordinance 2021-013, which mandates seismic evaluation and strengthening of wood-frame structures with soft, weak, or open-front wall lines (SWOF). OC Structural Engineering delivers complete, end-to-end engineering support so property owners can hit every required milestone, from the initial screening through final City approval.
Quick summary for property owners
Does my building need to comply
- Iswood-framed
- Was originally permitted before October 23, 1978
- Has ground-floor or basement parking or other large open area
- Has a soft, weak, or open-front wall line
- Has one or more stories above the open floor area
Single-family homes and accessory dwelling units are exempt. If you’ve received a Notice to Comply from Culver City, your building is officially part of the program.
How long do I have?
Every deadline is measured from the date on your specific Notice to Comply, not from the year the ordinance was originally adopted.
How OC Structural Engineering helps
We manage the engineering side of compliance for you, including:
- Screening reports
- Retrofit design and calculations
- City plan-check responses
- Structural observation during construction
- Final engineering close-out to support City sign-off
Ordinance 2021-013 requires Culver City property owners to evaluate and, where necessary, strengthen certain wood-frame buildings with soft, weak, or open-front wall lines. These buildings tend to perform poorly in earthquakes because the ground level lacks adequate lateral strength and stiffness.
Buildings included in the program
A building falls under this program if it:
- Is of wood-frame construction
- Has its original construction permit submitted before October 23, 1978
- Has a ground floor or basement level with parking or other large open floor area
- Contains one or more SWOF wall lines
- Has one or more stories above the open floor space
Single-family homes and accessory dwelling units are exempt building types.
Priority groups and notice dates
Culver City assigned compliance priority based on building size and configuration:
- More than 12 units, or
- More than 3 stories with more than 6 units
- Notices to Comply sent October 6, 2023
- 5–12 units (not Priority I)
- Notices to Comply sent February 20, 2024
- Duplexes, triplexes, townhomes, and all other SWOF buildings
- Notices to Comply sent July 5, 2024
Your actual deadlines are keyed to your building’s specific Notice to Comply date.
Required Compliance Milestones in Detail
1. Screening report, due one year after Notice to Comply
A licensed Civil or Structural Engineer performs a structural evaluation and prepares a Screening Report to determine whether the building is exempt or requires a seismic retrofit.
The screening typically covers:
- Review of the building’s configuration and wall lines
- Identification of SWOF conditions
- Preliminary assessment of load paths and diaphragms
- Review of foundations where accessible
If the building is documented as exempt, no retrofit is required under the ordinance.
2. Retrofit plans, due two years after Notice to Comply
If the screening shows a retrofit is required, the owner submits a complete retrofit plan set, generally including:
- Cover sheet and site plan
- Floor plans, elevations, and sections
- SWOF identification and justification of wall lines
- Structural calculations and lateral analysis
- Foundation plan and details
- Diaphragm analysis and strengthening where needed
- Verification and detailing for diaphragm aspect ratios (for example, 3:1 limits or mitigation)
- Required Culver City SWOF notes
- Tenant Impact Mitigation Plan, where applicable
3. Obtain permit and start construction, due three to four years after Notice
Once the City approves the retrofit plans, a licensed contractor pulls the building permit, and construction has to begin within one year of permit issuance, staying inside the overall three- to four-year window measured from the Notice date.
4. Complete construction, due five years after Notice
To satisfy the ordinance, the work must be finished, all required inspections passed, and the City must sign off the permit as “Final.”
What OC Structural Engineering Provides
Screening reports
- Field evaluation of the building’s soft-story conditions
- Identification of soft, weak, or open-front wall lines
- Evaluation of diaphragms, foundations, and lateral load paths
- Engineering determination of “Retrofit required” or “Exempt”
- Preparation of the formal screening documentation for the City
Retrofit plan sets
Prepared to meet Culver City’s SWOF requirements and typical reviewer expectations, which may include:
- Elevations and wall-line justification
- Full lateral system analysis
- Diaphragm design and ratio verification, with strengthening where necessary
- Foundation strengthening and new footings as required
- Beam and column upgrades
- Steel or wood special moment frame design
- Cantilevered column design in accordance with AISC provisions
- Collector and drag strut design in accordance with ASCE 7-16
- Material specifications and construction notes
- A coordinated structural calculation package
Permit and plan-check support
- Responding to Building Safety and SWOF reviewer comments
- Providing revised drawings and calculations when needed
- Preparing structural observation commitments and forms
- Supporting Housing Division clearance documentation when the project triggers it
Construction support
- Structural observation in accordance with Culver City CBC amendments and plan requirements
- Review of contractor RFIs relating to the structural design
- Site visits at key stages of the work
- Final observation letters or reports to support permit close-out
Why Soft-Story Retrofits Matter
Soft-story buildings are vulnerable during earthquakes because the ground floor often carries much less strength and stiffness than the levels above. Common issues include:
- Weak or open ground-floor walls due to parking or storefronts
- Large openings that shorten the effective length of shear walls
- Unreinforced or poorly detailed frames
- Irregular or discontinuous load paths
- Inadequate diaphragm support and chord detailing
These conditions can lead to excessive drift, localized failures, or collapse of the lower story in a strong earthquake. Culver City’s ordinance aims to reduce those risks, protect occupants, and preserve the city’s housing stock.
Culver City-Specific Considerations
Culver City reviewers typically look for:
- Clear identification and justification of SWOF wall lines
- Required cover-sheet notes and general notes specific to the SWOF program
- Compliance with material strength limitations and detailing requirements
- Appropriate structural observation commitments
- Shear wall lengths, drift limits, and seismic force-resistance system R-values that match code and local requirements
- Proper collector and drag strut design and detailing
- Foundation upgrades in line with CBC Chapters 18 and 19 as adopted and amended
- Anchorage and stability provisions for hillside or sloping sites
- Demonstrated continuity of the seismic load path from roof to foundation
Tenant notification and Housing Division requirements
For occupied buildings, Culver City may require:
- Written notification to current and prospective tenants
- Tenant protections when conditions become temporarily untenantable
- A Tenant Impact Mitigation Plan (TIMP) outlining how construction will affect residents
- Housing Division clearance before certain permits or work can proceed
OC Structural can assist with the engineering-related portions of these requirements and coordinate with property managers and ownership teams.
Capital improvement pass-through (optional for owners)
Culver City may allow owners to recover a portion of eligible retrofit costs through regulated rent increases, subject to:
- Timely application after project completion
- Documentation and verification of eligible costs
- Amortization limits
- Annual caps on rent increases
We can help document engineering and design-related expenses as part of a broader pass-through strategy.
A licensed Civil or Structural Engineer performs a structural evaluation and prepares a Screening Report to determine whether:
- The building is exempt, or
- The building requires seismic retrofit
- Review of the building’s configuration and wall lines
- Identification of SWOF conditions
- Preliminary assessment of load paths and diaphragms
- Review of foundations where accessible
If the screening indicates that retrofit is required, the owner must submit a complete retrofit plan set, which generally includes:
- Cover sheet and site plan
- Floor plans, elevations and sections
- SWOF identification and justification of wall lines
- Structural calculations and lateral analysis
- Foundation plan and details
- Diaphragm analysis and strengthening where needed
- Verification and detailing for diaphragm aspect ratios (for example, 3:1 limits or mitigation)
- Required Culver City SWOF notes
- Tenant Impact Mitigation Plan, where applicable
3. Obtain permit and start construction – due 3–4 years after Notice
After the City approves the retrofit plans:
- A licensed contractor pulls the building permit
- Construction must begin within one year of permit issuance, within the overall 3–4 year window from the Notice date
4. Complete construction – due 5 years after Notice
To satisfy the ordinance, the work must be completed and:
- All required inspections must be passed
- The City must sign off the permit as “Final”
Screening reports
OC Structural Engineering provides:
- Field evaluation of the building’s soft-story conditions
- Identification of soft, weak, or open-front wall lines
- Evaluation of diaphragms, foundations, and lateral load paths
- Engineering determination of “Retrofit required” or “Exempt”
- Preparation of the formal screening documentation for the City
Retrofit plan sets
Our retrofit plans are prepared to meet Culver City’s SWOF requirements and typical reviewer expectations, and may include:
- Elevations and wall-line justification
- Full lateral system analysis
- Diaphragm design and ratio verification, with strengthening where necessary
- Foundation strengthening and new footings as required
- Beam and column upgrades
- Steel or wood special moment frame design
- Cantilevered column design in accordance with AISC provisions
- Collector and drag strut design in accordance with ASCE 7-16
- Material specifications and construction notes
- A coordinated structural calculation package
Permit and plan-check support
We assist owners and contractors with the plan-check and permit process by:
- Responding to Building Safety and SWOF reviewer comments
- Providing revised drawings and calculations when needed
- Preparing structural observation commitments and forms
- Supporting Housing Division clearance documentation when triggered by the project
Construction support
During construction, OC Structural can provide:
- Structural observation in accordance with Culver City CBC amendments and plan requirements
- Review of contractor RFIs relating to the structural design
- Site visits at key stages of the work
- Final observation letters or reports to support permit close-out
- Weak or open ground-floor walls due to parking or storefronts
- Large openings that reduce the length of effective shear walls
- Unreinforced or poorly detailed frames
- Irregular or discontinuous load paths
- Inadequate diaphragm support and chord detailing
These conditions can lead to excessive drift, localized failures, or collapse of the lower story during a strong earthquake. The Culver City ordinance is intended to reduce these risks, protect occupants, and preserve the city’s housing stock.
- Clear identification and justification of SWOF wall lines
- Required cover-sheet notes and general notes specific to the SWOF program
- Compliance with material strength limitations and detailing requirements
- Appropriate structural observation commitments
- Shear wall lengths, drift limits, and seismic force-resistance system R-values that match code and local requirements
- Proper collector and drag strut design and detailing
- Foundation upgrades in line with CBC Chapters 18 and 19 as adopted and amended
- Anchorage and stability provisions for hillside or sloping sites
- Demonstrated continuity of the seismic load path from roof to foundation
Tenant notification and Housing Division requirements
For occupied buildings, Culver City may require:
- Written notification to current and prospective tenants
- Tenant protections when conditions are temporarily untenantable
- A Tenant Impact Mitigation Plan (TIMP) outlining how construction will affect residents
- Housing Division clearance before certain permits or work proceed
OC Structural can assist with the engineering-related portions of these requirements and coordinate with property managers and ownership teams.
Capital improvement pass-through (optional for owners)
Culver City may allow owners to recover a portion of eligible retrofit costs through regulated rent increases, subject to:
- Timely application after project completion
- Documentation and verification of eligible costs
- Amortization limits
- Annual caps on rent increases
We can help document engineering and design-related expenses as part of an owner’s larger pass-through strategy.
Frequently Asked Questions
I received a notice from Culver City. What does it mean?
It means your building was officially identified under Culver City Ordinance 2021-013 as a wood-frame structure with Soft, Weak, or Open-Front (SWOF) wall lines. You’re required to complete a Screening Report and follow the compliance timeline.
Does this mean my building is unsafe?
Not necessarily. It means your building has characteristics that make it more vulnerable during an earthquake. The program exists to evaluate that condition and, if needed, strengthen the building to reduce collapse risk.
What buildings are part of this program?
Your building is included if it meets all of the following:
- Wood-frame
- Two or more stories
- Ground-floor parking or large openings
- Built before October 23, 1978
- Identified with SWOF wall lines
These are the classic “tuck-under parking” or “open-front” soft-story structures.
What do I have to do first?
The first required step is the Screening Report, prepared by a licensed Civil or Structural Engineer. It determines whether your building is exempt (no retrofit needed) or required to move forward with engineering plans.
How long do I have to complete the Screening Report?
You have one year from the date your Notice to Comply was issued. This matters: your timeline is based on your specific notice date, not the year the ordinance was adopted.
What are the next steps after the screening?
If your building needs a retrofit:
- Retrofit Plans, due two years from notice
- Obtain Permit and Start Construction, by year three to four
- Complete Construction, by year five
If your building is exempt, the engineer documents this in the Screening Report and no further retrofit action is required.
Can my building be exempt?
Yes. Your engineer may determine that your building doesn’t meet SWOF criteria, was previously strengthened, or is structured in a way that doesn’t trigger the ordinance’s requirements. If exempt, the Screening Report documents this for the City.
What does the Retrofit Plan Set include?
Typical plan sets include a site plan and architectural sheets, SWOF identification, shear wall and moment frame design, foundation upgrades, diaphragm analysis, collector/drag strut detailing, structural calculations, required Culver City notes, and a Tenant Impact Mitigation Plan where applicable. Your engineer prepares this and submits it for plan check.
What happens during construction?
- The contractor pulls the permit, the engineer performs required structural observations, the City carries out inspections, and the project must receive final approval within five years of your notice date.
How much does the retrofit cost?
Engineering costs are fairly predictable, but construction costs vary considerably based on the building’s size, the number of openings, foundation condition, and the retrofit approach selected, whether that’s a moment frame, shear wall, or another method. We can give you a clearer picture once we’ve reviewed your screening results.
How long does engineering take?
Screening is usually quick, and retrofit plans typically take a few weeks once site access is granted. We provide a timeline right after our initial review.
What if I’m missing documents from the City?
Send us your Notice to Comply, a photo works fine, and we’ll tell you your deadlines, your compliance category, and exactly what needs to happen next.
Get Started
Whether your building received a Notice to Comply or you’d rather get ahead of the process, OC Structural Engineering is ready to manage the full engineering scope from start to finish.